Over/under billing (WIP) schedule

Enter each job's contract amount, estimated total cost, cost to date, and billed to date. The schedule shows percent complete, earned revenue, and how far billing is ahead of or behind the work, job by job and in total.

Your numbers stay on this device. Nothing is uploaded.

Over or under billing by jobJob 1Job 2Job 3Job 4Job 5Over-billingUnder-billingBilled to date minus earned revenue
Each job lands above or below the line: billed to date against earned revenue.

Jobs

JobContract amount, with change ordersEstimated total cost Cost to dateBilled to date% complete Earned revenueOver-billingUnder-billing

Portfolio totals

What gets checked

Your numbersThe mathThe checksVerifiedNot verified
A result that fails a check is marked not verified. It is never shown as correct.

How it works

  1. List the jobs. Add one row per job with its contract amount including approved change orders, estimated total cost, cost to date, and billed to date.
  2. Read each job. Percent complete is cost to date divided by estimated total cost. Earned revenue is the contract amount times that fraction. The difference between billed to date and earned revenue appears as over-billing or under-billing.
  3. Read the portfolio totals. Totals for every column are shown with the net over-billing or under-billing across all jobs.
  4. Check the certificate. Each check is listed with its result. Jobs running past their estimated cost or billed past their contract are named in a warning.
  5. Export or print. Download Excel or CSV, or print to PDF. The printout carries the verification result.

Worked example

Three made-up jobs at month end. The first is billed ahead of the work, and the other two are behind it.

JobContractEstimated costCost to dateBilled to date% completeEarned revenueOver-billingUnder-billing
Maple Street clinic$250,000.00$200,000.00$80,000.00$110,000.0040.00%$100,000.00$10,000.00
Harbor warehouse$180,000.00$150,000.00$100,000.00$112,500.0066.67%$120,000.00$7,500.00
Ridgeview school addition$95,500.00$81,000.00$27,000.00$30,000.0033.33%$31,833.33$1,833.33

Across the three jobs, $252,500.00 is billed against $251,833.33 of earned revenue. Over-billing totals $10,000.00 and under-billing totals $9,333.33, a net over-billing of $666.67. The portfolio is 48.03% complete by cost ($207,000.00 of $431,000.00).

The example uses made-up names and numbers.

Questions

Which method does the schedule use?

Cost-to-cost percent complete: cost to date divided by estimated total cost. Earned revenue is the contract amount times that fraction. Other ways of measuring progress, such as units installed, are not covered.

How is earned revenue rounded?

The contract amount in cents is multiplied by cost to date and divided by estimated total cost in whole-number math, then rounded to the nearest cent. The displayed percent is rounded separately to two decimals and is not used to compute earned revenue.

What happens when cost to date is above the estimated total cost?

The job shows more than 100% complete and earned revenue above the contract amount, exactly as the formula gives it, and a warning names the job. Nothing is capped or adjusted.

Does the contract amount include change orders?

It is whatever is typed in that column. The column is labelled for the contract amount including approved change orders, and the estimated total cost would then cover the same scope.

Where is my data stored?

On your device only. A draft is kept in this browser's storage. Nothing is sent to a server.

This tool calculates and checks numbers. It is not legal, tax, or medical advice.

Watch it run

A recording of this tool run on a made-up example is on YouTube, titled "Over/under billing calculator: a work in progress schedule by job".

The link opens YouTube, which is another site. This page loads nothing from it.

Template updates by email

At most four emails a year, when the free templates and rate tables for construction subcontractors are updated for a new quarter. Each has a one-click unsubscribe link.

Only the address typed here is sent, never anything from a file opened on this page. Nothing is added until the link in the confirm email is opened. Mathproven is a product of OpenSlot LLC, PO Box 96, Paintsville, KY 41240, USA. Privacy.