Subcontractor pay application builder

A pay application from a schedule of values works line by line: work billed before, plus work this period, plus materials stored, is completed and stored to date; retainage is taken on that amount; earned less retainage, minus what earlier certificates already paid, is the current payment due. Fill in your lines below and every figure is calculated, checked a second way, and carried into next month's application.

Your numbers stay on this device. Nothing is uploaded.

Completedand stored−Retainage−Previouspayments=PaymentdueEvery line is recomputed a second time
From work completed and stored down to the payment due.

Schedule of values

ItemDescriptionScheduled valuePrevious work This periodStored materialsCompleted & stored %Balance to finishRetainage

Summary

What gets checked

Your numbersThe mathThe checksVerifiedNot verified
A result that fails a check is marked not verified. It is never shown as correct.

How it works

  1. Enter the contract. Type the original contract sum, net change orders, and your retainage rates for completed work and stored materials.
  2. Fill in the schedule of values. Add one line per item with its scheduled value, work billed on earlier applications, work this period, and materials stored.
  3. Read the summary and the checks. Completed and stored, retainage, earned less retainage, and current payment due are calculated and verified. Any failed check is listed with the reason.
  4. Export or print. Download Excel or CSV, or print to PDF. The printout carries the verification result.
  5. Roll into next month. Start next month's application with this period's work moved into previous work and the certificates carried forward.

Worked example

A $100,000 electrical subcontract at 10% retainage, second application. Rough-in is finished and fixtures are half done, with $2,000 of fixtures stored on site.

ItemScheduled valuePrevious workThis periodStoredCompleted and storedRetainage
1 Rough-in$60,000.00$40,000.00$20,000.00$0.00$60,000.00$6,000.00
2 Fixtures$30,000.00$0.00$15,000.00$2,000.00$17,000.00$1,700.00
3 Trim and testing$10,000.00$0.00$0.00$0.00$0.00$0.00

Completed and stored: $60,000.00 + $17,000.00 + $0.00 = $77,000.00. Retainage at 10%: $6,000.00 + $1,700.00 = $7,700.00. Earned less retainage: $77,000.00 - $7,700.00 = $69,300.00. Application 1 billed $40,000.00 less $4,000.00 retainage, so $36,000.00 was certified before. Current payment due: $69,300.00 - $36,000.00 = $33,300.00. Balance to finish, plus retainage: $100,000.00 - $77,000.00 + $7,700.00 = $30,700.00.

The example uses made-up names and numbers.

Questions

How do I make a subcontractor pay application from my schedule of values?

List each schedule of values line with its scheduled value. For each line, add work billed on earlier applications, work done this period, and materials stored on site: that is completed and stored to date. Take retainage on each line at the contract's rate, add the lines up, subtract total retainage from total completed and stored, then subtract the previous certificates for payment. The worked example above shows every step with numbers.

Is retainage taken on the whole contract or on each period?

On what has been completed and stored to date, never on the whole contract up front. The amount held grows as work is billed. In the example, 10% of $77,000.00 is $7,700.00 held in total; application 1 held $4,000.00, so this application holds $3,700.00 more.

Can stored materials have a different retainage rate?

Yes. Some contracts set one rate on completed work and another on materials stored, for example 10% and 5%. The builder takes each line's work at the work rate and its stored materials at the stored rate, rounded to the cent per line.

How do change orders go on the pay application?

Enter the net of approved change orders with the original contract sum; together they are the contract sum to date. Add each change order as its own line in the schedule of values. A check confirms the lines add up to the contract sum to date, so a change order left off the schedule is caught.

What happens when retainage is released?

Enter the retainage released to date. It is subtracted from the retainage on the lines, which raises earned less retainage and so the payment due. A check refuses a release larger than the retainage held.

How is next month's application started?

Roll into next month: each line's work this period moves into previous work, and this application's earned less retainage becomes the previous certificates figure. Materials stored stay as they were, to be changed as they are installed; then only the new period's work is left to type.

Is this a specific industry form?

No. It is our own layout using generic progress billing terms: schedule of values, completed and stored to date, retainage, and current payment due. Check your contract for the format your general contractor requires.

How is retainage calculated?

Each line's completed work is multiplied by the work retainage rate and its stored materials by the stored materials rate, rounded to the cent per line. Retainage released to date is then subtracted from the total.

Where is my data stored?

On your device only. A draft is kept in this browser's storage, and you can save a file to your computer and reopen it later. Nothing is sent to a server.

What does the certificate show?

The list of checks that were run on your numbers, whether each passed, and the date. It travels with the export so the person receiving it can see the math was verified.

This tool calculates and checks numbers. It is not legal, tax, or medical advice.

Watch it run

A recording of this tool run on a made-up example is on YouTube, titled "Subcontractor pay application builder: schedule of values, retainage".

The link opens YouTube, which is another site. This page loads nothing from it.

Also inside Excel

The same calculation and the same checks run inside your own Excel workbook. The add-in fills the computed columns of your schedule of values and adds a summary sheet and a Certificate sheet. Nothing leaves the workbook.

Pay Application from Schedule of Values on the Microsoft marketplace.

Template updates by email